Project Development Timeline Print E-mail
COLOUR CODE: Completed; In Progress; Planned

2007

FINANCIAL

  • Recruitment of experienced management team
  • Acquired 100% interest in Dumont Project
  • Raised C$36.7 mn through private placements

EXPLORATION

  • Helicopter gradiometer survey completed
  • Review of historical resource estimates
  • Drilled 59 holes totaling 22,500 metres
  • Initiated metallurgical testing program

TECHNICAL REPORTS

  • 43-101 Micon Initial Resource Report, August 2007
  • Aker Kvaerner Conceptual Study, October 2007
2008

FINANCIAL

  • Proposed Private Placement

EXPLORATION

  • Drilled 43,000 m
  • Conducted environmental studies
  • Metallurgical testing and process development

TECHNICAL REPORTS

  • Genivar Environmental Baseline Study, April 2008
  • 43-101 Micon Updated Resource Report, April 2008
  • Aker/Genivar Updated Conceptual Study, July 2008
2009
  • Updated 43-101 Micon Resource Report, Jan. 2009
  • Resource drilling continues (22,000 m completed)
  • Environmental studies continue
  • Geotechnical/Hydrology drilling initiated
  • Metallurgical testing and process development continues
2010
  • Update 43-101 Micon Resource Report, Jan. 2010
  • Resource drilling continues
  • Scoping Studies
  • Environmental Impact Study initiated
  • Pre-feasibility study initiated
  • Metallurgical testing and process development completed
  • Initial Public Offering (subject to favourable market conditions)
2011
  • Resource drilling completed
  • Environmental Impact Study completed
  • Feasibility Study begins
2012
  • Project financing arranged
  • Development begins
2013
  • Development completed and initial production at Dumont commences
2014
  • Full production at Dumont