Project Development Timeline |
|
|
COLOUR CODE: Completed; In Progress; Planned
|
| 2007 |
|
FINANCIAL
- Recruitment of experienced management team
- Acquired 100% interest in Dumont Project
- Raised C$36.7 mn through private placements
EXPLORATION
- Helicopter gradiometer survey completed
- Review of historical resource estimates
- Drilled 59 holes totaling 22,500 metres
- Initiated metallurgical testing program
TECHNICAL REPORTS
- 43-101 Micon Initial Resource Report, August 2007
- Aker Kvaerner Conceptual Study, October 2007
|
| 2008 |
|
FINANCIAL
- Proposed Private Placement
EXPLORATION
- Drilled 43,000 m
- Conducted environmental studies
- Metallurgical testing and process development
TECHNICAL REPORTS
- Genivar Environmental Baseline Study, April 2008
- 43-101 Micon Updated Resource Report, April 2008
- Aker/Genivar Updated Conceptual Study, July 2008
|
| 2009 |
- Updated 43-101 Micon Resource Report, Jan. 2009
- Resource drilling continues (22,000 m completed)
- Environmental studies continue
- Geotechnical/Hydrology drilling initiated
- Metallurgical testing and process development continues
|
| 2010 |
- Update 43-101 Micon Resource Report, Jan. 2010
- Resource drilling continues
- Scoping Studies
- Environmental Impact Study initiated
- Pre-feasibility study initiated
- Metallurgical testing and process development completed
- Initial Public Offering (subject to favourable market conditions)
|
| 2011 |
- Resource drilling completed
- Environmental Impact Study completed
- Feasibility Study begins
|
| 2012 |
- Project financing arranged
- Development begins
|
| 2013 |
- Development completed and initial production at Dumont commences
|
| 2014 |
- Full production at Dumont
|
COLOUR CODE: Completed; In Progress; Planned
|